JL. KHM. Mansyur 229
Surabaya 60162 Indonesia
13 September 2022 Proyek, Produk,

Progress pengerjaan Tangki telah mencapai 70,67% dari total order project.

Progres instalasi tanki di lapangan
Raw Water Tank A : 83.74%
Raw Water Tank B : 83.71%
Demineralized Water Tank A : 69.88%
Demineralized Water Tank B : 80.47%
Fire Water Tank : 83.63%
Fuel Oil Tank A : 78.92%
Fuel Oil Tank B : 79.92%
SWRO Break Water Tank : 82.31%
BWRO Break Water Tank : 83.74%